A Pictorial History of the construction of the Broadway Station Building 2018

And so to 2018


The rush to finish before the arrival of the first trains.

January

Tiling of floors and walls in the toilet areas.




Electricians on site in store room and booking office/



Paneling of walls to dado height in booking hall.


Tiling of floor in booking hall started.


Platform side sees drainage installation and the commencement of slabbing.


Booking hall lamp being tested ready for fitting.


February

Plumbers are in the toilet areas.



Flooring in the Booking Hall almost finished.


Soon after paneling is finished and both station masters office and booking hall painted.



Slabbing finished on platform side commenced on the car park side.


March

Cubicle Separators in the toilets are fitted, areas fitted out with hand blowers and soap dispensers.


Doors have been fitted to the booking hall and are painted.


Booking hall finished , crowd barriers have been installed, also a clock and lamp.



First train for the volunteers .


To be continued.

3 comments:

  1. thanks for the series of yearly build achievements over the last 4 blogs , they bring back memories and the amazing hours of work put in by so many volunteers , many of whom I now know well , sharing the shifts in the cafe , aka Edwardian Refreshment Room .

    Keep safe and well everyone , Daily M .

    ReplyDelete
  2. A wonderful Timeline , worthy of display on the platform for our visitors to enjoy, any chance for this summer when we hopefully resume ?

    keep safe and well , daily M.

    ReplyDelete
  3. Excellent pictures and blog. Thanks.
    Regards, Paul.

    ReplyDelete