And so to 2018
The rush to finish before the arrival of the first trains.
January
Tiling of floors and walls in the toilet areas.
Electricians on site in store room and booking office/
Tiling of floor in booking hall started.
Platform side sees drainage installation and the commencement of slabbing.
Booking hall lamp being tested ready for fitting.
February
Plumbers are in the toilet areas.
Flooring in the Booking Hall almost finished.
Soon after paneling is finished and both station masters office and booking hall painted.
Slabbing finished on platform side commenced on the car park side.
March
Cubicle Separators in the toilets are fitted, areas fitted out with hand blowers and soap dispensers.
Doors have been fitted to the booking hall and are painted.
Booking hall finished , crowd barriers have been installed, also a clock and lamp.
First train for the volunteers .
To be continued.
thanks for the series of yearly build achievements over the last 4 blogs , they bring back memories and the amazing hours of work put in by so many volunteers , many of whom I now know well , sharing the shifts in the cafe , aka Edwardian Refreshment Room .
ReplyDeleteKeep safe and well everyone , Daily M .
A wonderful Timeline , worthy of display on the platform for our visitors to enjoy, any chance for this summer when we hopefully resume ?
ReplyDeletekeep safe and well , daily M.
Excellent pictures and blog. Thanks.
ReplyDeleteRegards, Paul.