And so to 2016
January 2016
Sewage and drainage pipes completed from inside to outside.
March 2016
Floor Installation added , then concrete laid on top
Outside drainage and man holes completed on car park side.
Brick work up to Plinth headers , then the door frames and over the coming months as the brick work grows in height , eventually window sills and window frames.
Internal walls constructed fitted with insulation in between it and the external walls.
August to November 2016
Station brick work at a height that now required scaffolding to continue bricklaying.
Internally a real and a false chimney are being built.
Arch over the entrance to the toilet is completed, the positioning of the commemorative stone block is finalized and cemented in place.
The start of the fitting of the Joists .