Thursday 8 April 2021

A Short Week

 Week Commencing 5th April 2021


No Monday gang this week due to it being Easter Monday , so it was only the Wednesday gang on site this week and thanks to Terry again for the photos.

 Peter K was in his portakabin continuing the production of spear fencing , whilst outside Mike gave the latest one a coating of red primer.

Down at the end of platform 2 , Rod Terry and Keith were laying the final slabs for the retaining wall .


 Its that man with the shovel again !


And elsewhere Chris and Dave were cleaning up the fallen branches from around the site ready for maybe a bonfire next Monday.


Remember as from the  13th April ,  the passenger trains will commence running. Details for booking tickets are on our website .