Friday 15 March 2024

Spring Time At Broadway ?

 Week Commencing 11th March 2024


Firstly the Monday shot of platform 2 , Block work to damp course almost there , just a few blocks for the inner walls and fire place to do.


Back on the other side yet another coat of black on the running board from Ian


And Dave was having a trial fit of some new edging , made by our good friends from the Carpentry dept down at Winchcombe.


Brian was making some blocks to hold up his new sign.


Ian gave the new edging a coat of primer


And Brian fitted his blocks !


Up on the spear fencing saw Peter  endlessly rubbing down 


Wednesday

The one piece of edging for the running board had bolt holes through it , the new running board has sunken bolt holes and the edging should cover them . two new ends were manufactured and they replaced either end.


We finally got a new replacement for the broken soap dispenser .


Pat was on killing moss duties.


The running in board got flipped over and a final coat of light stone was applied , maybe next week if we have enough volunteers on site it will get put back up ?


Billy goat came out , as it was dry to clean up the pavement down the drive


And Peter 


Dave