Monday

4 of us braved the cold but dry Monday .

The last of the refurbished bins was placed under the stairs , showing off its newly painted lid !


Vic was down the drive after using up the last of the wood treatment on the fence, then decided to clear some of the debris away from the last weeks storm.


Mike decided to give the platform edge a good clean off .


And Kevin was working on his edging to the small garden. Myself was in container 1 sorting out the life expired paint .


Wednesday

Down to 3 volunteers , sickness in the air .

Over on platform 2 , no brick laying , days and nights are too cold still . But Neil and Jo have been at work clearing the rear of the building and transpoting the soil into the trucks.


Mike got way past the station canopy with his edge cleaning , you can tell the difference from the photo .


Later he went back to the Spear Fencing and gave a couple of panels a coating of light stone paint.



There was a big unloading at the end of the day , the delivery of the Door and window frames, and glass  for the platform 2 building . just need to find a proper storage place until its needed !