Thursday 10 December 2020

One More Week to go!

 Wednesday 9th December


Pat our maintenance man was checking out the motors and as can be seen by the short grass on the embankments he has been very busy.






















Terry, Rod and Tony were again on platform 2 working on the South slope. Digging out a trench, placing slabs as a stop edge and filling up with concrete.





The  Finished edging at the bottom of the ramp

 

 

The trench dug ready for the slabs up the slope to the existing edging.







Pete, Vic & Brian were on the drive embankment removing unwanted plants with Dave & Ian moving the wheel barrows with rubbish to the bonfire.




















The station looking very quiet.




Mike and Peter K were erecting more palisade fencing and adding paint. Sorry no photo the camera played up.


Finally someone regaining his childhood, jumping in puddles.



See you next week.

2 comments:

  1. Just to say it's great to see all the spearhead fencing going up on P2, it really makes a massive difference to the appearance and how "finished" it all looks from P1. Carry on the good work!

    ReplyDelete
  2. The station looks very nice and platform 2 is coming along very well.
    Regards, Paul.